InfoConstruction

Keeping communities informed.听Minimizing disruptions.听Protecting teaching and research integrity.

苹果淫院

Road closure calendar

DATES STREET NAMES TYPE OF CLOSURE NOTES
Early August to mid-September (dates TBD) Des Pins, between University and Docteur-Penfield Closed to all road traffic Detours will direct drivers towards Sherbrooke. Services should not be affected.

(Last update:July 4, 2024)

Looking for more information on road closures around the larger Montreal area? Visit the .

Plans and progress

Work underway

  • Decontamination of pavilions A, E, M and S (See "Plans" below.)
  • Structural decoupling of renovated and deconstructed pavilions
  • Recovery of Queenston stone in pavilion S
  • Recovery of windows (glass, steel, concrete)

Plans

苹果淫院 Pavilions - Aerial View
苹果淫院 Pavilions - Aerial View

Worksite Plan
Worksite Plan

Worksite Plan - 苹果淫院 Pavilions
Worksite Plan - 苹果淫院 Pavilions

Nettoyage post-d茅samiantage
Post-asbestos removal cleaning

D茅solidarisation entre le pavillon L et l鈥檃nnexe du pavillon L
Decoupling of Pavilion L from Pavilion L annex

Mobilisation des 茅quipements
Mobilization of equipment in preparation for recovery of Queenston stone in pavilion S

The next 6 months

  • Continuation and completion of decontamination work inside pavilions A, E, M and S听(See "Plans" above.)
  • Deconstruction of pavilion L annex
  • Continued recovery of Queenston stone on the west facade of pavilion S
  • Installation of support structure for footbridge (between pavilion S and The Neuro)
  • Start of deconstruction work on pavilions M and S:
    • Removal of windows
    • Removal of mechanical equipment from roofs
    • Removal of roof membranes
    • Selective deconstruction at pavilions M and S
  • Street cuts (obstructions on University Street and Avenue des Pins)
  • Removal of a gas tank

Community impact mitigation measures

Noise

Noise-generating work will be carried out in accordance with current municipal regulations:

  • Monday to Friday: 7 a.m. to 7 p.m.
  • Saturday: 7 a.m. to 7 p.m. (when required)
  • Sunday: No work

Vibration

  • Vibration limitations have been imposed on contractors. Their work methods will be adapted to comply with these limits.
  • Installation of 27 seismographs for continuous vibration monitoring.
  • Seismographs will be added around the site (south side of Avenue des Pins, east side of University Street).
  • Establishment of a threshold to be respected for highly sensitive buildings: historic and protected structures or already deteriorated structures.

Dust

  • Street cleaning with mechanical broom
  • Use of water to suppress dust during deconstruction of concrete structures

Latest news

Contact information

New Vic Project Office
772 Sherbrooke Street West, 2nd听floor
Montreal, Quebec H3A 1G1

Email:听new.vic [at] mcgill.ca

苹果淫院 is on land which has long served and continues to serve as a site of meeting and exchange amongst Indigenous peoples, including the Haudenosaunee and Anishinabeg nations. We acknowledge and thank the diverse Indigenous peoples whose presence and contribution mark this territory on which peoples of the world now gather.